One of the UK's biggest housing developers, which is building 128 homes in Pannal, has said it can no longer afford to pay for a cycle route on Leeds Road, despite being legally obliged to do so.
Bellway Homes was granted planning permission for its Jubilee Park development on the site of the former Dunlopillo factory in 2017. Homes are being sold there for upwards of £316,000.
Bellway Homes committed to paying for a cycle route on the A61 from the bridge over the River Crimple in Pannal to the Fulwith Mill Lane junction. This was done by a section 106 agreement, which housebuilders pay to mitigate for the cost of development.
However, more than four years after being granted permission to build the homes, the developer today asked Harrogate Borough Council's planning committee to remove the agreement, which it called "unreasonable" due to a change in government cycle scheme standards.
Harrogate Borough Council housing officer Kate Broadbank, who wrote a report to councillors recommending they approve the removal of the section 106 agreement, said the cycle route would now cost £980,000 due to the new government standards.
Ms Broadbank wrote in the report that "it would not be reasonable" to expect the developer to pay for it all.
Liberal Democrat councillor Hannah Gostlow, who represents Knaresborough Scriven Park, asked if this meant the taxpayer would now foot the rest of the bill if the cycle route ever gets built.
Harrogate Borough Council's chief planner John Worthington said this was an "impossible question to answer”.
Councillors agreed to remove the section 106 agreement and accept the £189,000 offer by 7 votes to none, with three councillors abstaining.
0