Harrogate’s Otley Road to be dug up again

Harrogate’s Otley Road is to be dug up for the second time in just over a year.

Work is due to start on Monday, February 20 and last for two weeks subject to external factors such as weather.

North Yorkshire County Council contractors spent three months creating the first phase of the Otley Road cycleway between September and December 2021.

The same stretch of road is now set to be disturbed again to allow the firm City Fibre to install fibre optic cables that will enable people to receive full fibre-enabled broadband services.

City Fibre is nearing the end of a £46 million upgrade of broadband connectivity in Harrogate, Knaresborough and Ripon. Otley Road will be the last area to be completed in Harrogate.

The county council was due to begin remedial work early this year on cycleway design faults and defects highlighted by residents and Harrogate District Cycle Action.

But a report to councillors for a meeting tomorrow says:

“In May 2022 the fibre optic network company City Fibre contacted North Yorkshire County Council with a request to install fibre optic cables down the full length of the newly constructed cycleway.

“We have negotiated with City Fibre to reinstate the full width of the cycleway at their expense. We will therefore carry out our outstanding remedial works once City Fibre have installed their apparatus.”


Read more:


Kim Johnston, City Fibre area manager, said in a press release sent out previously that the firm will repair defects at its own expense when it makes good the road. She said:

“We are working closely with North Yorkshire County Council in this area as we understand that the footways on Otley Road have undergone recent resurfacing.

“With the council’s agreement, as part of City Fibre’s essential development works, the footways will be restored, including repairs to defects that North Yorkshire County Council were due to carry out.”