More than £1.5m of taxpayers’ money has already been spent on plans for a major redevelopment of Harrogate Convention Centre before the project has been approved.
In what is set to be one of its biggest decisions in recent history, Harrogate Borough Council will next summer vote on the proposed project, which is currently at the design stage and could cost £47m over three phases.
Figures obtained by the Local Democracy Reporting Service show £1.1m has so far been spent on contracts for design and feasibility works, while £275,000 has been spent on a first phase business case and £179,050 on an outline business case.
Councillor Graham Swift, deputy leader and cabinet member for economic growth at the council, said these works have been a key part of the planning process and that they will help the authority weigh up the benefits and risks before making a final decision. He said: