A Pateley Bridge resident has expressed frustration at a delay in the completion of major roadworks in the town.
Temporary traffic lights have been on the B6265 at Red Brae Bank, Bewerley since storms caused a landslip in February 2020.
In October, North Yorkshire County Council began a £480,000 scheme to stabilise the road, which is on the steep slope out of Pateley to Greenhow Hill — the highest point in the Harrogate district.
The road was due to close on October 17 and re-open on completion of the work on December 16. But it remains closed , with the scheme now set to continue for at least another fortnight.
Former Pateley town councillor Chris Hawkesworth, who lives nearby, said he had been unable to find out why the scheme had been delayed and when it would be completed.
Mr Hawkesworth said large vehicles that ignored road closed signs and then turned on the narrow, steep hill had damaged his farmhouse wall and post box.
He said local people had to make an 11-mile detour to get into Pateley Bridge even though it is less than a mile away and businesses in the town were losing customers because of problems accessing the area.
Chris Hawkesworth on the B6265 near his house.
He added some couriers refused to deliver in the area and rubbish was going uncollected. He said:
Andrew Murday, the Liberal Democrat county councillor for Pateley Bridge and Nidderdale, told the Stray Ferret he had spoken to Mr Hawkesworth about the matter.
Cllr Murday said the project was "geologically difficult" and had proved trickier to resolve than expected but it was a major scheme that was close to completion.
He said he understood how frustrating it was and sympathised with those affected, adding one delivery lorry had got stuck on the minor road Peat Lane when the driver tried to find a shortcut around the diversion. Cllr Murday said