If you are accessing this story via Facebook but you are a subscriber then you will be unable to access the story. Facebook wants you to stay and read in the app and your login details are not shared with Facebook. If you experience problems with accessing the news but have subscribed, please contact subscriptions@thestrayferret.co.uk. In a time of both misinformation and too much information, quality journalism is more crucial than ever. By subscribing, you can help us get the story right.
Already a subscriber? Log in here.
21
Apr 2020
https://www.youtube.com/watch?v=ZxUUPkM7NQI&feature=youtu.be
The transformation of the Harrogate Convention Centre into a 500-bed surge hospital has been a real feat of engineering and cooperation.
Work started on the NHS Nightingale Yorkshire and the Humber three weeks ago and required 13 miles of copper, 15,000m² of vinyl, 18,000m² of hygienic walls, 1,000 pieces of IT equipment, 100 miles of cables and more than seven million litres of oxygen.
It also needed more than 600 people working together from the NHS, BAM Construction and the Armed Forces - with more than 30,000 hours of labour.
When the work began the director of the HCC Paula Lorimer said she had to bring back security, cleaning and stewarding teams to help the construction team: