Harrogate’s Otley Road cycleway has cost £2.2m so far
by
Feb 15, 2023
Otley Road cycle path
The Otley Road cycle route

The Otley Road cycleway in Harrogate has cost £2,234,000 so far  — almost triple the amount awarded to contractors to construct the first phase.

Hull civil engineering firm PBS Construction was awarded £827,000 in 2021 to build phase one from Harlow Moor Road to Cold Bath Road.

The much-criticised route opened in January last year but subsequent remedial work and design fees for phase two of the project — which has since been scrapped — increased the cost significantly.

The widening of the Otley Road and Harlow Moor Road junction was the main remedial work.

The figures are contained in a North Yorkshire County Council report, which raises questions over whether the council had sufficient funds to complete the second phase of the scheme.

Councillor Keane Duncan, the Conservative executive member for highways and transportation at North Yorkshire County Council, said phase two had been dropped because it lacked public support.

But the report reveals the council has just £565,000 remaining of the £4,275,000 it secured in 2018 from the government’s National Productivity Investment Fund for measures that enabled development and business growth in west Harrogate

The funding and spending figures contained in the report are reproduced below.

Otley Road cycle way

Otley Road cycle way

According to the document, council officers received “multiple reports” about the design and construction of the cycleway from residents and groups such as Harrogate District Cycle Action after it opened. It adds:

“These were then reviewed with our design consultants WSP, and a list of remedial works have now been prepared.

“These remedial works were planned to be completed in the early part of 2023. However, in May 2022 the fibre optic network company City Fibre contacted North Yorkshire County Council with a request to install fibre optic cables down the full length of the newly constructed cycleway.

“We have negotiated with City Fibre to reinstate the full width of the cycleway at their expense. We will therefore carry out our outstanding remedial works once City Fibre have installed their apparatus.”

The report adds £60,000 of the remaining funds are expected to cover these remedial works.


Read more:


The council has said it will come up with new traffic calming measures in the west of Harrogate to compensate for scrapping phase two of the scheme, which would have extended the cycleway from Cold Bath Road towards Beech Grove.

It still has aspirations to construct phase three out of town to Cardale Park at an unspecified time in the future.

North Yorkshire County Council’s highways area manager Melisa Burnham said:

“Although construction costs increased to £970,000 following completion, this was still within our anticipated budget. The increase was a result of additional design works and remedials found whilst on site.

“The remaining costs include design, feasibility, surveys and utility diversions required to deliver phase one and two of the cycleway, and the Harlow Moor Road junction improvement to date.”

 