Two major local leisure centre projects in Harrogate and Knaresborough have been delayed — and will cost more than expected.
The new North Yorkshire Council gave its first update on the refurbishment of Harrogate Hydro and the construction of Knaresborough Leisure and Wellness Centre today.
It revealed the Hydro is now due to re-open in August following a £13.5 million refurbishment.
The facility, which will be renamed Harrogate Leisure and Wellness Centre, was originally due to re-open in January this year and the project was due to cost £11.8 million.
But it now won't be open for the start of the summer holidays.
A council statement today said:
The new Knaresborough Leisure and Wellness Centre is due to open in November at a cost of £17.6 million.
The project was initially due to re-open at the end of summer and cost £17 million.
The existing Knaresborough Pool was due to be demolished once the new facility was open.
But to keep construction costs as low as possible, the current pool will close and start to be demolished in early September following the opening of the Harrogate Leisure and Wellness Centre.
It means Knaresborough is likely to be without a pool for two months.
Once the existing pool has been demolished, a new play area in front of the new Knaresborough Leisure and Wellness Centre will be installed.
Cllr Simon Myers, the council’s executive member for culture, arts and housing, said: