If you are accessing this story via Facebook but you are a subscriber then you will be unable to access the story. Facebook wants you to stay and read in the app and your login details are not shared with Facebook. If you experience problems with accessing the news but have subscribed, please contact subscriptions@thestrayferret.co.uk. In a time of both misinformation and too much information, quality journalism is more crucial than ever. By subscribing, you can help us get the story right.
Already a subscriber? Log in here.
29
Jul 2022

A developer looks set to be given extra time to complete a report into ground stability for a 30-house scheme in Ripon.
Wetherby firm Newett Homes received planning permission in February to build 30 homes at Springfield Close. Its previous bid to build 38 homes was refused.
But Harrogate Borough Council's decision was conditional on the company producing a satisfactory ground stability report within four months. Ripon is a notorious area for sink holes.
The report has yet to be produced but next week's council planning committee looks set to grant Newett Homes a four-month extension.
A council officer's report to the planning committee recommends it awards extra time but adds that if the report is not produced in another four months "the application be refused" due to concerns over unstable and contaminated land.
The report says:
It adds that given the amount of work that has already been carried out "it would be counterproductive to refuse the application at this stage, as it would result in additional unnecessary work for both the local authority and the applicant and could delay the site coming forward".
Councillors will decide on Tuesday next week whether to accept the officer's recommendation.