Detailed designs for Harrogate's controversial £7.9 million Station Gateway project are to be drawn up, it was agreed today.
Councillors voted to press ahead with the next stage of the scheme, which could see the pedestrianisation of James Street and Station Parade reduced to one lane of traffic,
The project, which aims to create a more attractive entrance to the town with greater priority for pedestrians and cyclists. is part of the government’s Transforming Cities Fund.
There are similar projects being run in Selby and Skipton but transport officials said Harrogate has proved the most contentious due to resistance from some businesses are worried about the impact on trade.
A recent public consultation, however, revealed public support for a town centre less dominated by cars.
A total of 45% of 1,101 respondents were in favour of the full pedestrianisation of James Street; 32% said no changes should be made and 17% backed a partial pedestrianisation.
For Station Parade, 49% favoured an option to reduce traffic to one lane, while 27% said it should be retained as two lanes and 24% said neither option was workable.
Speaking at today's North Yorkshire County Council meeting, councillor Don Mackenzie, executive member for access, said:
More detailed designs will now be completed before a business case is drawn up and a final decision is made.
A county council report said the impact on parking and traffic would be kept to a minimum, with just 45 out of 915 parking spaces lost.
The report also said reducing Station Parade to one lane would increase the average car journey time by 53 seconds, or by 1 minute 14 seconds with James Street fully pedestrianised.
Some businesses fear the removal of parking spaces and traffic lanes will mean busier roads and fewer shoppers.
Councillor Mackenzie added:
Further public consultation will now take place in autumn following the development of detailed designs and a business case.
If approved, construction could begin in summer 2022 with completion by March 2023.