Harrogate's Otley Road is to be dug up for the second time in just over a year.
Work is due to start on Monday, February 20 and last for two weeks subject to external factors such as weather.
North Yorkshire County Council contractors spent three months creating the first phase of the Otley Road cycleway between September and December 2021.
The same stretch of road is now set to be disturbed again to allow the firm City Fibre to install fibre optic cables that will enable people to receive full fibre-enabled broadband services.
City Fibre is nearing the end of a £46 million upgrade of broadband connectivity in Harrogate, Knaresborough and Ripon. Otley Road will be the last area to be completed in Harrogate.
The county council was due to begin remedial work early this year on cycleway design faults and defects highlighted by residents and Harrogate District Cycle Action.
But a report to councillors for a meeting tomorrow says: