The full extent of the multi-million pound overspend on the junction 47 upgrade on the A1(M) remains unknown — six months after the project ended.
The scheme near Flaxby, which was originally budgeted to cost £7.7m, finished in April, seven months later than planned.
North Yorkshire County Council revealed more than a year ago that costs had increased to £10m and has not given an updated figure since.
The Stray Ferret asked the council this week when a figure would be published.
Richard Binks, head of major projects and infrastructure at the council, said:
Officials celebrate the completion of works.
Cllr Keane Duncan, the council’s executive member for highways, previously said the project had reduced congestion and improved road safety, adding: