This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Cookie settingsACCEPT
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities...
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT
    • Politics
    • Transport
    • Lifestyle
    • Community
    • Business
    • Crime
    • Environment
    • Health
    • Education
    • Sport
    • Harrogate
    • Ripon
    • Knaresborough
    • Boroughbridge
    • Pateley Bridge
    • Masham
  • What's On
  • Offers
  • Latest Jobs
  • Podcasts

Interested in advertising with us?

Advertise with us

  • News & Features
  • Your Area
  • What's On
  • Offers
  • Latest Jobs
  • Podcasts
  • Politics
  • Transport
  • Lifestyle
  • Community
  • Business
  • Crime
  • Environment
  • Health
  • Education
  • Sport
Advertise with us
Subscribe
  • Home
  • Latest News
  • Transport

We want to hear from you

Tell us your opinions and views on what we cover

Contact us
Connect with us
  • About us
  • Advertise your job
  • Correction and complaints
Download on App StoreDownload on Google Play Store
  • Terms and Conditions
  • Privacy Statement
  • Comments Participation T&Cs
Trust In Journalism

Copyright © 2020 The Stray Ferret Ltd, All Rights Reserved

Site by Show + Tell

Subscribe to trusted local news

In a time of both misinformation and too much information, quality journalism is more crucial than ever. By subscribing, you can help us get the story right.

  • Subscription costs less than £1 a week with an annual plan.

Already a subscriber? Log in here.

15

Feb

Last Updated: 20/02/2025
Transport
Transport

Why are some local roadworks worked on through the night, but others last for ages?

by John Grainger

| 15 Feb, 2025
Comment

0

microsoftteams-image-10-7
Some roadworks carry on through the night - but why?

There appears to be no end to roadworks – they're here to stay, in one place or another. Whether it’s the council’s resurfacing work in Ripon city centre or Northern Powergrid slicing Harrogate’s York Place down to a single lane of traffic, there’s no dodging the diggers for long.

But while some roadwork schemes can seem half-forgotten by the people who start them, others seem to attract special attention. One hole in the ground can be deserted while just around the corner on a side street, men can be seen working around the clock under floodlights.

So, what’s the rationale here? How do the council and utility companies decide what resources will go where, and how intensively roadworks will be treated?

roadworks-1

.

It turns out several factors come into play. According to a spokesperson for Openreach, the company that lays the fibre broadband network, safety and the prevention of disruption are key issues.

They said:

If the problem poses a significant risk to safety, infrastructure, or service continuity, immediate action is often required regardless of the time.

High-impact issues affecting a large number of customers or critical services may necessitate after-hours work to minimise downtime and disruption.

They added that some tasks may be too hazardous to perform at night, or during the day, or in adverse weather conditions.

Sometimes, Openreach has to coordinate with other utility companies, which might only be available during specific hours.

The spokesperson said:

For example, if one of our street cabinets is damaged in a vehicle collision, we have to notify the local power company (all our cabs are powered) as we may need to get them to switch off the power and carry out safety checks before our engineers can start work.

Sometimes, we might only be given permission to work at night to avoid disruption to road-users.

roadworks-4

Some roadworks can seem to last forever

Similar considerations guide the other utility providers. Sometimes, the water, gas or electricity supply needs to be cut off, so the company will work at night to minimise any inconvenience to residents during the day.

The duration of any roadworks is also affected by a variety of factors. A spokesperson for Yorkshire Water told us:

We can’t speak to work outside of the water and wastewater network, but there are a number of factors that might influence how long a job takes.

For emergency repairs: the depth of our network underground and how much excavation is required; whether there are other utilities or authorities’ assets involved; how complex the fault, and therefore the repair, is.

The majority of our network is buried underground, so the scope of repairs can change once we dig down and see the asset that requires work.

The time taken for pipe fixes to cure, or for tarmac to cure (this is often one of the reasons why sites can look like they aren't being worked on – colleagues can't do anything whilst waiting for this).

All the companies we contacted – Yorkshire Water, Openreach, Nothern Gas Networks, Northern Powergrid – and North Yorkshire Council said that their workers are sometimes subjected to verbal abuse by irate motorists.

The Yorkshire Water spokesperson even suggested that some had taken matters into their own hands by rearranging temporary street furniture. They said:

[People can help by] following the guidance on signage and not moving the signage out of the way.

We will reopen roads as soon as it is safe to do so – barriers are in place to protect road-users, pedestrians and our on-site teams.

The Northern Gas Networks spokesperson said there was a reason why some sites can look abandoned:

We appreciate that if you pass by a site and can’t see anyone working, it might be frustrating, but the work is still ongoing.

We may be busy carrying out a different section of the job, or monitoring it remotely.

In the meantime, The Openreach spokesperson appealed for understanding. They said:

[People can help by] just showing patience with traffic management, driving past slowly and safely and following any pedestrian redirection signage.

Asked about these issues, Cllr Keane Duncan, North Yorkshire Council's executive member for highways and transport, told the Stray Ferret that the council always schedules its own roadworks to limit disruption, avoiding peak times and full road closures where possible.

He also said the council was acting to mitigate the problems:

We are [...] taking the toughest possible approach to manage works by third parties, such as utility companies, with the introduction of the first lane rental scheme in the North of England.

Building on our existing permit scheme, we will introduce a £2,500 daily charge for peak-time works on the busiest and most sensitive routes, including routes in Harrogate.

This will incentivise third parties to work outside of peak hours, to work to schedule and to cooperate with each other.

During all works, we ask the public for their patience and co-operation, and to plan their journeys and follow diversions. We urge against removing barriers and to comply with temporary speed limits to ensure the safety of the public and our staff. 