Five weeks of travel disruption on Otley Road in Harrogate will begin on Monday due to work by Northern Gas Networks .
Work will take place around the Otley Road/Harlow Moor Road junction and is scheduled to finish on Friday September 3.
The news is unlikely to be welcomed by commuters or businesses that have had to contend with an almost continuous set of roadworks on the road since January.
Yorkshire Water dug up the surface to re-lay water pipes and Northern Powergrid did the same to relocate electricity infrastructure.
Next week’s works are to prepare for the delayed Otley Road cycle route.
Read more
- £827,100 contract to start work on Otley Road cycle path in September
- Delayed Otley Road cycle path set to begin in August
North Yorkshire County Council told the Stray Ferret that work on the cycle route will begin on September 6.
Nigel Smith, head of highway operations at the council, said:
“Utility works by Northern Gas Networks and Northern Powergrid remain to be completed before work can begin on phase 1 of the Otley Road cycle scheme.
“Northern Gas Networks is scheduled to be on site between August 2 and September 3, and Northern Powergrid between August 16 and 27. BT has confirmed its works can be carried out during the Harlow Moor Road junction improvement.
“The anticipated start date for phase 1 of the Otley Road cycle scheme, which includes the Harlow Moor Road junction improvement, is September 6 this year, subject to the above utilities completing their work.”