Long-term work to upgrade junction 47 on the A1(M) at Flaxby has now been completed.
The project, to improve infrastructure before more houses are built in Knaresborough and Green Hammerton, is at least £2.3 million over budget and took seven months longer to complete than planned.
The original budget was £7 million. This had increased to £10 million by September and the final cost has yet to be revealed.
The A59 corridor has been identified in the Harrogate district Local Plan 2014-35, which outlines where development can take place, as an area of rapid increase in residential and business growth.
Work on the junction began in September 2020 and this week became fully operational. The traffic lights have been switched on for the first time and all lanes are now open.
Three of the four slip roads, on and off the roundabout, have been widened to increase capacity.
Traffic signals are now in place on the roundabout to manage traffic flow and a T-junction has been added between the A168 and A59 to help drivers on the York side turning onto the A59.
A lane has been added to the west of junction 47 between the A1 and Flaxby roundabout so there will be two lanes in each direction between those two roundabouts.