To continue reading this article, subscribe to the Stray Ferret for as little as £1 a week
Already a subscriber? Log in here.
25
Oct 2021
Ripon Leisure Centre will only be partially open when the city's new swimming pool comes on stream in seven weeks’ time.
Harrogate Borough Council (HBC) has confirmed that the leisure centre's ground floor will remain closed while 'further ground investigatory work and any remedial action required is considered.'
The multi-million pound project, due to include a six-lane pool, fully-refurbished leisure centre and outside play areas, was initially scheduled for completion in May, but ground stabilisation work known as grouting, contributed to a six-month hold up.
Last week HBC announced a revised date of 8 December for the opening of the pool.
Now, however, there is a further delay in delivery of the complete scheme, which is already more than £3 million over budget.
A spokesperson for HBC, said:
The leisure centre gym has been moved and can now be accessed via a temporary first floor entrance, but a spin studio and other facilities that would have been on the ground floor, will not be available when the pool opens.
The original £10.2 million contract awarded to construction company and principal contractor Willmott Dixon in November 2019, stipulated a completion date of May 2021.
Following the extension of the contract, known costs for the scheme currently stand at £13,555,662.
0