They were supposed to have moved three weeks ago, but the four-way traffic lights on one of Harrogate’s busiest roads are still bringing daily misery to hundreds of motorists.
Northern Gas Networks began work replacing metal pipes with plastic pipes beneath Skipton Road on July 13.
The project has required two sets of traffic lights on Skipton Road, plus lights on the adjoining King’s Road and Woodfield Road.
On September 18, Chris Reed, site manager at NGN, apologised for any inconvenience caused by the delayed project and assured the Stray Ferret the four-way lights would be replaced by two-way lights the following day as the project moved further along Skipton Road.
But since then the four-way lights have remained.
Besides delaying motorists, the lights have blighted the lives of residents and business.
Read more:
- Coronavirus backlog sees roadworks double in Harrogate district
- Bilton club claims loss of earnings for roadworks
Bilton Working Men’s Club on Skipton Road has filed a claim for loss of earnings against NGN.
The Stray Ferret asked NGN if it could finally say when the four-way lights would be removed.
But Richard White, the company’s business operations lead, was unable to give a date.
Mr White said NGN was now resurfacing the Skipton Road end of King’s Road. He added:
“This is a major, complex project, involving the removal of a number of ageing metal gas pipes some of which are 70 or 80-years-old.”
He said completion of the entire project “remains on schedule for the end of November”. But no date before then for the end of the four-way lights was given.
Bilton club claims loss of earnings for roadworksBilton Working Men’s Club is filing a claim for loss of earnings caused by the long-running roadworks outside its premises on Skipton Road.
Northern Gas Networks began work replacing metal pipes with plastic pipes beneath the road on 13 July.
Four-way traffic lights in the area have caused tailbacks not only on Skipton Road but also on adjoining King’s Road and Woodfield Road.
Alan Huddart, the club treasurer, said the work had made it more difficult for people to get to the club, which reopened after lockdown on 4 July, and some had assumed it was closed. Mr Huddart added:
“We have received a compensation pack and will be submitting a claim. The roadworks have had a dire impact.
“They’ve probably reduced our takings by 20 per cent.”

The roadworks immediately outside Bilton Working Men’s Club.
Chris Reed, site manager at Northern Gas Networks, said:
“We want to apologise to Bilton Working Men’s Club for any impact that our works have had as the project progresses. We will work with them to resolve any compensation claim.”
Mr Reed said the project had been delayed because the old pipes, some of which were 70 years old, were deeper than the plans indicated.
Read more:
- Coronavirus backlog sees roadworks double in Harrogate district
- Tea shop plans for former tanning salon in Bilton
The roadworks are now expected to finish by the end of November but the worst delays could be over.
Richard White, business operations lead for Northern Gas Networks, said:
“The temporary traffic lights have been removed at the junctions of Skipton Road with Woodfield Road, and of Skipton Road with King’s Road.
“There are two-way traffic lights still in place on Skipton Road, and these are now away from the junction and are near Jewson builders’ merchants. We expect these two-way, and three-way temporary traffic lights at junctions with side roads, to move along Skipton Road as the project progresses.”