Exclusive: Council spent £1.9m on consultants for scrapped Harrogate Convention Centre plans
by
Last updated Apr 8, 2024
Photo of Harrogate Convention Centre against a dramatic-looking sky.

Almost £2 million of taxpayers’ money has been spent on consultants to come up with plans to upgrade Harrogate Convention Centre that have now been scrapped.

North Yorkshire Council and its predecessor Harrogate Borough Council have hired various consultants since 2016 as part of the long running saga to redevelop the convention centre.

So far none of the work has been carried out and last month North Yorkshire Council revealed it had abandoned previous plans drawn up by Harrogate Borough Council and recruited another firm of consultants called 31ten to carry out ‘soft market testing’ on the future use of the events and exhibition complex.

North Yorkshire Council refused to reveal at the time how much it had paid the 31ten — prompting the Stray Ferret to submit a freedom of information request.

We asked not only how much had been awarded to the London firm but also how much had been spent on consultants for all work involving the possible upgrade of the convention centre.

The response said 31Ten had been paid £23,000 plus VAT for work that is expected to be concluded by ‘late spring’. This figure pales in comparison to the overall sum awarded to consultants since 2016.

The freedom of information response said besides funding awarded to 31Ten “the remaining £1,948,590 relates to historic spend committed by Harrogate Borough Council”.

Harrogate Borough Council was abolished a year ago and succeeded by North Yorkshire Council.

The response added:

“It is North Yorkshire Council’s intention to use internal resource to support future proposals for Harrogate Convention Centre, and minimise spend with external consultants, wherever possible.”

‘More affordable’ way forward

North Yorkshire Council’s Conservative-controlled executive agreed last month to scrap a two-phase development plan for the building drawn up eight years ago after being told the cost of the first phase had soared to £57.2 million.

Instead it agreed to come up with a “more affordable” way forward. Centre director Paula Lorimer, who last year called for the refurbishment, said she had now changed her mind and agreed with the new approach.

The way forward will be guided by 31ten’s findings. The freedom of information response said:

“The aim of the soft market testing is to assist North Yorkshire Council in assessing the options for the future development and operation of Harrogate Convention Centre. Options may include, but are not limited to, alternative delivery and funding models, partnership working, alternative uses for parts of the site, and asset ownership.”

North Yorkshire Council currently subsidises the convention centre to the tune of £2.7 million a year.

The centre opened in 1982 and has a 2,000-seat auditorium and 13,000 square metres of exhibition space.